|
BACKGROUND OF CONS
In
February 2007, a smoldering fire developed in a condo’s chimney
from the furnace in the basement. After the fire was
extinguished and the Fire Investigator started his investigation
it was discovered that the chimney and its surrounds did not
match with the approved specifications. When asked how this
would have passed inspection the Investigator’s comment was,
“What inspection?” This was the first step in the formation of
CONS. The fact that there were no independent inspections during
the process of condo construction was a surprise to all of us.
Yet, that is the reality when multi-unit residential buildings
(condos and apartments) are built. It is left to the
builder/developer to insure that the building is built to
specifications. In the same building, two months later, there
was extensive flooding from a top floor unit. Upon
investigation it was found that during construction a nail had
punctured a water pipe behind a baseboard. During the
intervening two year period water had slowly leaked from one
wall to adjoining walls. Shortly thereafter, another unit in
the same building experienced a similar problem. However, this
time it was found that water was entering the unit through an
outside wall. A result of this second occurrence of a unit
experiencing water leaks it was decided to inspect the entire
building for water penetration. Of the 63 units in the building
61 were found to have some form of water penetration. In
addition four units had high mould content.
The
following June, a group of condo representatives met to discuss
problems that were experienced in condominium buildings What
was found that although there were some unique problems, there
was one common problem, which was water infiltration. It was
subsequently discovered that many other condos were having
problems with poor workmanship, as follows:
·
Balcony doors not properly installed leading to leaks in units
·
Light
fixtures not properly waterproofed
·
Angle
irons above windows slanting inwards, thus directing water
inside the unit
·
Same
building – angle irons cut too short allowing water ingress
-
Vapour barrier not secured to back of brick, allowing water
to run down into units
-
Windows without flashing around them.
-
In
many instances on the outside of a building the vapour
barrier (Tyvek) was either missing or ripped, allowing the
elements entry into the building.
At
that meeting the group identified two major problems that needed
to be addressed. One was the need to improve the quality of
construction practices and the second was to review and update
the Condominium Act
Many
condo owners did not want the subject of shoddy work to become
public knowledge, which is understandable to a point, as it
would affect the value of their property in the market place.
However, all this would do was support and protect the
developer. This had to be stopped.
In
July, following the June meeting, an appointment was made to
meet with Jamie Muir, Minister of Service Nova Scotia. At that
meeting the group articulated the two major concerns expressed
at the June meeting. Namely, (1) to improve the quality of
construction there should be frequent and unannounced
inspections during the construction of a new condominium; (2)
there should be longer extended warranties of at least five
years; (3) that the Condominium Act should be updated to allow
for easier and cheaper resolutions of disputes between boards
and owners.
In
August 2007, the CONS Steering Committee gave a presentation, to
HRM Mayor Kelly, with their respective staffs in attendance. The
recommendations were: (1) that the developer should be
responsible to repair all defects caused by faulty workmanship,
not for one year, but for up to 10 years; (2) that the developer
posts a bond of 5% of the total cost of the building with the
government for a period of five years, at which time, if there
were no claims, that money, plus interest, would be returned to
him. This would prevent the developer from declaring bankruptcy
thus avoiding any claims against him; (3) that both levels of
government work together to enforce rigorous inspection
procedures. And that these inspections by conducted by
Engineers/Architects independent of the government and
developer, but contracted by the government to carry out the
inspections on behalf of the government, not leaving it as it
now stands where the developer is responsible for the
inspections; (4) that all builders be licensed by the province
in order to build homes and other dwellings, prior to them
obtaining permission to commence building; (5) that the entire
Condominium Act of Nova Scotia be overhauled so that boards have
the power to enforce bylaws without the costly process of
entering into arbitration every time a by-law is infringed.
It was
also felt that an education process be established for real
estate agents and buyers alike so that everyone is aware of what
is involved when one buys a condo.
On 14
November 2007, over 40 condo owners attended the first official
meeting of CONS, where an executive was elected to ensure that
the aims of CONS would be met by both levels of government
across this province. In five months the interest had grown from
12 attendees at the first meeting on 20 June, to over 40 at the
second meeting.
Following our July 2007 meeting with Minister Muir, he did
follow through in addressing our two critical concerns. The
Government engaged Novus Consulting to do a review of the home
owner protection measures that presently exist in the province
and the Government also appointed a committee to review the
Condominium Act. CONS was an active participant in both
reviews.
On
September 26, 2008, Novus Consulting tabled their Final Report
on Home Owner Protection and on September 1, 2011, the
Government proclaimed the amended Condominium Act into law.
Both of those Reports addressed the key issues that lead to CONS
coming into existence. Both, the Final Home Owner Protection
Report and changes to the Condominium Act can be downloaded from
the Service Nova Scotia web site.
|